Your browser does not support JavaScript! Skip to main content
Free 30-day trial DO-178C Handbook RapiCoupling Preview DO-178C Multicore Training Multicore Resources
Rapita Systems
 

Industry leading verification tools

Rapita Verification Suite (RVS)

RapiTest - Functional testing for critical software RapiCover - Low-overhead coverage analysis for critical software RapiTime - In-depth execution time analysis for critical software RapiTask - RTOS scheduling visualization RapiCoverZero - Zero-footprint coverage analysis RapitimeZero - Zero-footprint timing analysis RapiTaskZero - Zero-footprint event-level scheduling analysis RVS Qualification Kits - Tool qualification for DO-178 B/C and ISO 26262 projects RapiCoupling - DCCC analysis

Multicore Verification

MACH178 - Multicore Avionics Certification for High-integrity DO-178C projects MACH178 Foundations - Lay the groundwork for A(M)C 20-193 compliance Multicore Timing Solution - Solving the challenges of multicore timing analysis RapiDaemon - Analyze interference in multicore systems

Other

RTBx - The ultimate data logging solution Sim68020 - Simulation for the Motorola 68020 microprocessor

RVS Software Policy

Software licensing Product life cycle policy RVS Assurance issue policy RVS development roadmap

Industry leading verification services

Engineering Services

V&V Services Data Coupling & Control Coupling Object code verification Qualification Training Consultancy Tool Integration Support

Latest from Rapita HQ

Latest news

Rapita partners with Asterios Technologies to deliver solutions in multicore certification
SAIF Autonomy to use RVS to verify their groundbreaking AI platform
RVS 3.22 Launched
Hybrid electric pioneers, Ascendance, join Rapita Systems Trailblazer Partnership Program
View News

Latest from the Rapita blog

How emulation can reduce avionics verification costs: Sim68020
Multicore timing analysis: to instrument or not to instrument
How to certify multicore processors - what is everyone asking?
Data Coupling Basics in DO-178C
View Blog

Latest discovery pages

Military Drone Certifying Unmanned Aircraft Systems
control_tower DO-278A Guidance: Introduction to RTCA DO-278 approval
Picture of a car ISO 26262
DCCC Image Data Coupling & Control Coupling
View Discovery pages

Upcoming events

DASC 2025
2025-09-14
DO-178C Multicore In-person Training (Fort Worth, TX)
2025-10-01
DO-178C Multicore In-person Training (Toulouse)
2025-11-04
HISC 2025
2025-11-13
View Events

Technical resources for industry professionals

Latest White papers

Mitigation of interference in multicore processors for A(M)C 20-193
Sysgo WP
Developing DO-178C and ED-12C-certifiable multicore software
DO178C Handbook
Efficient Verification Through the DO-178C Life Cycle
View White papers

Latest Videos

How to make AI safe in autonomous systems with SAIF
Rapita Systems - Safety Through Quality
Simulation for the Motorola 68020 microprocessor with Sim68020
AI-driven Requirements Traceability for Faster Testing and Certification
View Videos

Latest Case studies

GMV case study front cover
GMV verify ISO26262 automotive software with RVS
Kappa: Verifying Airborne Video Systems for Air-to-Air Refueling using RVS
Supporting DanLaw with unit testing and code coverage analysis for automotive software
View Case studies

Other Resources

 Webinars

 Brochures

 Product briefs

 Technical notes

 Research projects

 Multicore resources

Discover Rapita

Who we are

The company menu

  • About us
  • Customers
  • Distributors
  • Locations
  • Partners
  • Research projects
  • Contact us
  • Careers
  • Working at Rapita

Industries

  Civil Aviation (DO-178C)   Automotive (ISO 26262)   Military & Defense   Space

US office

+1 248-957-9801
info@rapitasystems.com Rapita Systems, Inc., 41131 Vincenti Ct., Novi, MI 48375, USA

UK office

+44 (0)1904 413945
info@rapitasystems.com Rapita Systems Ltd., Atlas House, Osbaldwick Link Road, York, YO10 3JB, UK

Spain office

+34 93 351 02 05
info@rapitasystems.com Rapita Systems S.L., Parc UPC, Edificio K2M, c/ Jordi Girona, 1-3, Barcelona 08034, Spain
Back to Top Contact Us

DO-178C - Stage of Involvement 1

2022-03-01

SOI #1 - Planning Review

Following on from our first blog (Introduction to DO-178C), we provide you an insight into the first stage of involvement review for the DO-178C process.

DO-178 SOI 1

Planning is a crucial part of DO-178C compliance, and it sets the scene for your project’s activities and the efficiency of those activities in later stages. You can save effort in your DO-178C planning by using a set of template planning documents as a starting point. The development of a set of plans covering all components of the Design Assurance process is a cornerstone of DO-178C.

As part of this activity, the following plans must be developed:

  • Plan for Software Aspects of Certification (PSAC): a description of the software you plan to develop, the hardware environment it will be used in, the design assurance processes you will follow, and how you will demonstrate compliance, including how you will verify your implemented code and any commercial tools you will use in your verification. This acts as the parent planning document.
  • Software Development Plan (SDP): a description of the software development processes and the software life cycle that is used to satisfy DO-178C objectives.
  • Software Verification Plan (SVP): a description of the verification processes (Reviews, Analyses and Tests) used to satisfy DO-178C objectives.
  • Software Configuration Management Plan (SCMP): a description of the methods and environment that will be used to configure all the design data and compliance evidence needed to achieve DO-178C certification.
  • Software Quality Assurance Plan (SQAP): a description of the methods and associated records that will be used to ensure that DO-178C quality assurance objectives are satisfied.

For higher DAL levels, as well as producing the above planning documents, you will also need to establish and document the standards you will use for Requirements, Design, and Code, documenting the methods, rules, and tools you will use to ensure complete and consistent generation of these items in a way that will meet DO-178C and project objectives. It pays to put effort into writing your standards – having well thought out standards reduces the chance of incurring rework costs later due to issues that could be addressed through having better standards, such as producing unverifiable requirements.

DO-178C Stages of Involvement

When your plans are complete and have been reviewed and signed off internally, it will be time to take the first step in the compliance process by having the SOI#1 review with your certification authority. The SOI#1 review is typically a “desk” review performed by the authority, who will thoroughly review all plans and standards to ensure that all applicable objectives of DO-178C and any relevant supplements will be satisfied if the development proceeds as documented in your plans. This review will result in either a report documenting any observations or findings that must be resolved, or acceptance that your plans and standards are compliant. When your plans have been accepted, the next step is to follow them!

Learn more about DO-178C by downloading the free 70-page handbook here.

DO-178C webinars

DO178C webinars

White papers

Mitigation of interference in multicore processors for A(M)C 20-193
Sysgo WP Developing DO-178C and ED-12C-certifiable multicore software
DO178C Handbook Efficient Verification Through the DO-178C Life Cycle
A Commercial Solution for Safety-Critical Multicore Timing Analysis

Related blog posts

News from the Certification Together International Conference in Toulouse

.
2011-12-13

4 key benefits of structural coverage for DO-178B systems

.
2011-11-10

DO-178C: The Next Avionics Safety Standard tutorial at the SIGAda conference

.
2011-11-10

Agile programming and tool qualification

.
2010-11-12

Pagination

  • First page « First
  • Previous page ‹ Previous
  • Page 1
  • Page 2
  • Page 3
  • Page 4
  • Current page 5
  • Solutions
    • Rapita Verification Suite
    • RapiTest
    • RapiCover
    • RapiTime
    • RapiTask
    • MACH178

    • Verification and Validation Services
    • Qualification
    • Training
    • Integration
  • Latest
  • Latest menu

    • News
    • Blog
    • Events
    • Videos
  • Downloads
  • Downloads menu

    • Brochures
    • Webinars
    • White Papers
    • Case Studies
    • Product briefs
    • Technical notes
    • Software licensing
  • Company
  • Company menu

    • About Rapita
    • Careers
    • Customers
    • Distributors
    • Industries
    • Locations
    • Partners
    • Research projects
    • Contact
  • Discover
    • Multicore Timing Analysis
    • Embedded Software Testing Tools
    • Worst Case Execution Time
    • WCET Tools
    • Code coverage for Ada, C & C++
    • MC/DC Coverage
    • Verifying additional code for DO-178C
    • Timing analysis (WCET) & Code coverage for MATLAB® Simulink®
    • Data Coupling & Control Coupling
    • Aerospace Software Testing
    • DO-178C
    • Meeting DO-178C Objectives
    • AC 20-193 and AMC 20-193
    • Meeting A(M)C 20-193 Objectives
    • Certifying eVTOL
    • Cerifying UAS

All materials © Rapita Systems Ltd. 2025 - All rights reserved | Privacy information | Trademark notice Subscribe to our newsletter